Resupply subcontracting¶
In resupply subcontracting, a company supplies the components of its product to a subcontractor, who manufactures the product, then delivers the finished product to the contracting company’s warehouse.
This article covers how to configure a subcontracted product and walk through the resupply subcontracting process.
Configuration¶
To use the resupply subcontractor workflow, contractors must first configure products with a vendor pricelist and a subcontracting-type BoM. Each component must then be configured with the appropriate route.
The pricelist allows the contracting company to purchase the product from the vendor (subcontractor) through a PO, while the BoM allows the product to be manufactured externally by the subcontractor. Routes are applied to each component in order to be properly sent from the contractor to the subcontractor.
Configure product vendor¶
To configure a product’s vendor for resupply subcontracting, navigate to , and select a product, or create a new one.
On the product form, click the Purchase tab and add the product’s subcontractor as a vendor by clicking Add a line. Select the subcontractor in the Vendor drop-down menu.
Then, enter the price of the product in the Price field.
Finally, set a lead time for the product in the Delivery Lead Time field to specify the number of days for the subcontractor to receive components, produce the product, and deliver the finished good.
Note
Since contractors are not responsible for manufacturing the final product, there is no need to configure manufacturing lead times on a BoM. Instead, provide only a single Delivery Lead Time on the vendor pricelist, factoring in the duration for the subcontractor to receive the components from the contractor, manufacture the product, and deliver the finished good back to the contractor.
Configure BoM¶
After specifying the vendor, configure a subcontracting-type BoM for the product. To start, click the Bill of Materials smart button on the product’s page. Then, select the desired BoM or create a new one.
Tip
Alternatively, navigate to , and select the BoM for the subcontracted product.
In the BoM Type field, select the Subcontracting option. Then, add one or more subcontractors in the Subcontractors field below.
Finally, add all necessary components in the Components tab. To add a new component, click Add a line. Then, select the component in the Component drop-down menu, and specify the required quantity in the Quantity field.
Configure components¶
In resupply subcontracting, each component must be individually configured with the Resupply Subcontractor on Order route. This allows the components to be transferred from the contractor to the subcontractor when a PO is made for the subcontracted product.
To configure a component’s route, select the component’s name in the Components tab, and click the (Internal link) arrow. Alternatively, navigate to , and select the component.
On the component product form, click on the Inventory tab. Then, in the Routes section, select the Resupply Subcontractor on Order route.
Important
Repeat the process for every component that must be sent to the subcontractor.
Workflow¶
The resupply subcontracting workflow begins by creating a PO to purchase the product from the subcontractor (1).
The contractor (YourCompany) then confirms the PO, which creates both a resupply order to transfer the components and a receipt to receive the final product (2) from the subcontractor.
Next, the contractor validates the transfer of components to the subcontractor (3). The subcontractor begins producing the product.
Once the product has been produced and received, the contractor validates the receipt (6) to trigger inventory moves from the subcontractor to the company’s stock (4, 5).
Create and confirm PO¶
To create a PO for the subcontracted product, navigate to and click New.
Begin filling out the PO by selecting a subcontractor from the Vendor drop-down menu. In the Products tab, click Add a product to create a new product line. Select the subcontracted product in the Product field, and enter the quantity in the Quantity field.
After adding the product, the Expected Arrival field is updated with the finished product’s expected delivery date, as configured earlier with the vendor Delivery Lead Time.
Finally, click Confirm Order to confirm the PO. A receipt and a resupply order are automatically created, accessible via the Receipt and Resupply smart buttons at the top of the form.
Validate resupply order¶
Click the Resupply smart button at the top of the PO to open the resupply order, and click Validate to confirm that the components have been sent to the subcontractor.
Alternatively, navigate to the app, click the (#) To Process button on the Resupply Subcontractor card, and select the relevant resupply order. Then, click Validate to confirm that the components have been sent to the subcontractor.
Process receipt¶
After the resupply order is confirmed, the subcontractor manufactures the product and delivers the finished good back to the contracting company.
To receive the finished product from the subcontractor, click the Receive Products button on the PO, or click the Receipt smart button at the top of the page. Then, click Validate to enter the incoming shipment into inventory.
Note
If multi-step inventory flows are enabled, additional transfers must be validated to enter the incoming product into stock.
Track inventory moves¶
After validating the receipt, Odoo automatically generates inventory moves to track the movement of subcontracted products between locations. To view these inventory moves, navigate to .
In resupply subcontracting, Odoo first transfers any product components to a dedicated Subcontracting Location. A virtual location called Production then consumes the components and produces the finished good. Once produced, the good then moves back to the Subcontracting Location before finally entering the contractor’s stock when the receipt is validated.